Withnell Bay LNG Jetty
General Information
-
The LNG jetty is a single berth loading facility for LNG tankers
-
A gangway to accommodation all tankers is located on the loading platform and is manoeuvred on board by the berthing crane
-
Six breasting dolphins with double Yokohama fenders and panels extending from LT 0.5m to LAT +7.1m comprise the berth face
-
Each dolphin is equipped with a double release hook and capstan for spring line moorings
Principal Dimensions
-
The berth pocket is dredged to 13.2m
-
The loading platform is equipment with four 16" LNG loading/vapour return arms
-
The berth can accommodate vessels from 190m to 300m LOA and in the following size range 30,000 - 150,000 DWT
Entrance and Departure
-
Approach track from Woodside Channel Buoy to Buoy No 7 Dist 6.1nm least depth 13.2m
-
The channel from No 7 to No 13 is 3.4nm long and 250m wide
-
The minimum dredged depth is 12.0m at LAT
-
The manoeuvring area is dredged to 12.15m with a turning circle 600m in diameter